Bearing degradation predicted on Compressor C-201
C-201 · CPF Train 02
Confidence
87%
ImpactUnplanned shutdown risk ≈ $920K · 36 hrs deferment
Probable causes
- Vibration 1x/2x harmonics rising over 21 days
- Lube oil particle count above alarm
- Load cycling above design envelope
Recommended actions
- Schedule inspection within 7 days
- Reserve bearing BR-550
- Verify lubrication system
- Combine task with planned shutdown window
Data analysed
- 180 days of vibration history
- 43 maintenance records
- 16 comparable compressors
- Current operating conditions